For investors interested in large photovoltaic power plant investments, we offer management of the full investment process, settled based on specific milestones (stages):

  • Stage I – Project assignment for implementation by the Investor or acceptance of a project proposed by Newsolar
    • Finalization of the project price at the „ready-to-build” stage
    • Determining the installment amounts for each milestone
    • Signing of the investment agreement
    • Establishment of a special purpose vehicle (SPV)
  • Stage II – Obtaining the building permit conditions (WZ)
    • Payment by the Investor of the agreed amount for the first installment for service implementation
    • Preparation of the project concept and Project Information Card (KIP)
    • Full administrative process to obtain environmental and building permit decisions
    • Obtaining a final building permit decision for the SPV
  • Stage III – Obtaining the connection conditions permit (WPE)
    • Payment by the Investor of the agreed amount for the second installment for service implementation
    • SPV’s advance payment for connection conditions
    • Full administrative process to obtain the connection conditions permit
    • Obtaining connection conditions for the SPV
  • Stage IV – Obtaining the construction permit (PnB)
    • Payment by the Investor of the agreed amount for the third installment for service implementation
    • Preparation of the construction project
    • Full administrative process to obtain the construction permit
    • Obtaining a final construction permit (PnB)
  • Stage V – Final project settlement
    • Payment by the Investor of the agreed amount for the final fourth installment for service implementation
    • Investor’s acquisition of 100% shares in the SPV

Additionally, the scope mentioned above can be expanded to include construction and installation works, selection of contractors, as well as service and maintenance of the installation.