For investors interested in large photovoltaic power plant investments, we offer management of the full investment process, settled based on specific milestones (stages):
- Stage I – Project assignment for implementation by the Investor or acceptance of a project proposed by Newsolar
- Finalization of the project price at the „ready-to-build” stage
- Determining the installment amounts for each milestone
- Signing of the investment agreement
- Establishment of a special purpose vehicle (SPV)
- Stage II – Obtaining the building permit conditions (WZ)
- Payment by the Investor of the agreed amount for the first installment for service implementation
- Preparation of the project concept and Project Information Card (KIP)
- Full administrative process to obtain environmental and building permit decisions
- Obtaining a final building permit decision for the SPV
- Stage III – Obtaining the connection conditions permit (WPE)
- Payment by the Investor of the agreed amount for the second installment for service implementation
- SPV’s advance payment for connection conditions
- Full administrative process to obtain the connection conditions permit
- Obtaining connection conditions for the SPV
- Stage IV – Obtaining the construction permit (PnB)
- Payment by the Investor of the agreed amount for the third installment for service implementation
- Preparation of the construction project
- Full administrative process to obtain the construction permit
- Obtaining a final construction permit (PnB)
- Stage V – Final project settlement
- Payment by the Investor of the agreed amount for the final fourth installment for service implementation
- Investor’s acquisition of 100% shares in the SPV
Additionally, the scope mentioned above can be expanded to include construction and installation works, selection of contractors, as well as service and maintenance of the installation.